Asbestos abatement in Acker Hall is complete. Old lighting and fans were removed when ceiling tiles were removed. The carpet, floor tiles and adhesive were removed in Acker, the hallway to the back stairwell, the stage and storage room.

The stage and storage room have been emptied and are ready for demolition. New accessible restrooms will be built in their place, making for seamless use for all members and guests.

Acker Hall serves as the “fellowship hall” for Pacific Hills. Flooring and ceiling upgrades are planned. The ramp from the existing Elevette will be demolished, as the new replacement elevator will open at floor level.